6th May 2015
Only those who have registered for the MATLAB with CC will be allowed to use them. Others will not be allowed to use licenses. This will be implemented from 06/05/2015 10 AM onwards. Those who have not registerd yet, please register in the following link
https://cc.iitm.ac.in/node/251
20th April, 2015
Since the file system is full, we would be running a script on 20th April 2015 in Virgo, which would clear all the files and folders in the scratch except the directory of the current running job. So make sure you don't keep any useful data in the scratch.
Note : There is no backup for scratch folders by HPCE team.
6th April, 2015
License registration process will be started for intel.
20th March, 2015
This is a survey which would facilitate Computer Center to get information about the users using institute's licenses for executing any of the pre/post/solver of the commercial software (wherever applicable). This will help CC to plan Renewal/Purchase of licenses.
All license usage will be on 80:20 basis.(80% from the departments and 20% from Computer Center).
Form needs to be submitted on or before 20/3/2015.
Only on registration, licenses will be made available by the license server and without registration licenses will not be available for Institute's commercial software running in Computer Centre.
Those who have already registered for intel compilers, need not register again for the same.
All the users of the commercial applications listed in the registration form are requested to register in the link below
http://goo.gl/forms/eeotL5l2Zd
23th February, 2015
System will be released to the users.
19th February, 2015
Shutdown of Virgo for Manitenance.
14th January, 2015
Comsol Training
COMSOL training details are as below:
City: Chennai, Tamil Nadu
Time: 9:00am - 5:00pm
Date: February 5th & February 6th, 2015
Location: Hotel Vestin Park, Egmore, Chennai -08
More information about COMSOL training courses can be found here:
:http://www.comsol.co.in/events/id/35681/
:http://www.comsol.co.in/events/id/35691/
The outline for COMSOL training program is as below:
Please feel free to contact us for further information.
17th December 2014
Libra cluster is down due to File system issues, it will be up and running within today.
9th December 2014
GNR cluster is down due to power failure.
17th November 2014
The number of jobs for Gaussian Users have been increased to 50. Dear Gaussian users kindly plan your jobs accordingly.
14th November 2014
The number of jobs for Gaussian Users have been restricted to 20. Dear Gaussian users kindly plan your job accordingly.
31st July 2014
Virgo system will not be available to users on 31/7/2014 from 9AM to 5PM in view of UPS maintenance.
Kindly schedule your jobs accordingly.
Inconvenience caused is regretted.
1st May 2014
There is an issue in the network/vm of the license server, the issue is posted to the vendor, he will be coming tomorrow since today is a holiday. Hopefully by tomorrow it will be fixed. Thanks for your patience and co-ordination.
7th April 2014
The Virgo system is up and running. The submitted jobs got killed and the jobs which were in queue also got killed because of the system problem.
Kindly resubmit your jobs.
Kindly delete all jobs files created in scratch directory by these unfinished jobs.
3rd April 2014
The virgo super cluster has crashed due to an unavoidable incident, you will be intimated as soon as the cluster is up and ready to use. Your patience is appreciated.
2nd April 2014
Release of 256 core cluster -- gnr
We are happy to announce the release of a 256 cores machine, called "GNR" in the P.G. Senapathy Computer Centre at IIT Madras. This machines is specially built for the usage of B.Tech. and DD students of IITM. The details can be found at:
https://cc.iitm.ac.in/
All new accounts for B.Tech. and DD students will be created in "GNR". Please contact hpce@iitm.ac.in for creating your account.
The B.Tech. and DD students, who are currently using "Virgo" cluster for executing their jobs, are requested to transfer their accounts to "GNR" as soon as possible.
Please write to hpce@iitm.ac.in to receive the account info from your smail account. Please note that all your files will automatically be transferred from Virgo to GNR. Your VIrgo account will be DEACTIVATED on April 21 at 12 noon. Hence, you must contact HPCE Team before this deadline.
20th Janaury 2013
Ansys 15 & Fluent 15 installed
To load the latest Ansys 15 & Fluent 15 version in virgo use the below path.
ANSYS & Fluent = /sware/ansys15/ansys_inc/v150/
15th Janaury 2013
Comsole 4.4 installed
To load the latest Comsole 4.4 version in virgo use the below path.
COMSOLE = /sware/comsol/comsol4.4/bin
18 th November 2013
The licenses running on the existing license server(leo0-10.65.0.75) will be stopped on 18/11/2013 and the new license server(cclicserver.iitm.ac.in) will be functional from 18/11/2013. In this transition some of the running jobs will get killed and users are requested to submit such killed jobs again.
The List of Software License in the New License Server as follows
The inconvenience caused is regretted.
Kindly refer to the following link for updating your license server (Note: You must login to see the information)
https://cc.iitm.ac.in/node/33
Orientation program on Ansys/Fluent>/p>
There are lot of changes in the Modules of Ansys/Fluent. Ansys/Fluent is withdrawing some features of Ansys/Fluent and introducing new features in Ansys/Fluent. Hence an orientation program for Ansys/Fluent has been arranged in Computer Center. It becomes essential for Ansys/Fluent users to attend this orientation program to use Ansys/Fluent without any difficulty.
Venue : Central Lecture Theatre(CLT)
Date : 12th & 13th of November 2013
Time : 10am to 5 pm
Dear Users,
The Virgo system is ready and is under observation.
Users can submit jobs.
If there are any problems, kindly contact HPCE @ 5997 or send mail to hpce@iitm.ac.in
Dear Users,
The GPFS file systems crashed and killed the running jobs.
Users are requested to submit their jobs again.
Please plan your jobs for the next ten days as there will be a planned shutdown on 8/7/2013 and 9/7/2013 for firmware upgrade of the file systems.
Inconvenience caused is regretted
Dear Virgo Users,
An one day workshop on IBM HPC is being held on 18th June at ED cad lab. Interested can participate by registering their names at https://10.21.203.248/IBM
Dear Virgo Users,
A Intel workshop is being held on 13th june at ED cad lab. Students and faculty of differernt departments can participate by registering at https://10.21.203.248/Inteltraining.
Dear Virgo Users,
The System is now available and the users can start using it.
The System was unavailable due to some file system issues.
Dear Users of Virgo,
IBM engineers are still working on the GPFS file system.As soon as the file system is ready, the system will be released to the users.We will inform the users through mail, once the system is ready. Inconvenience caused is regretted
Dear Users of Virgo,
we are experiencing some problem with the file systems resulting in very slow read/write. IBM engineers claim that they have identified the issue and have suggested some remedial actions. To incorporate these we need to take the system for maintenance on Monday the 15th of April from 9.00 am to 5.00 pm.The cluster will not be available to the users during this time. Inconvenience caused is regretted
The Virgo cluster has file system issues and to fix these issues, the system will be taken for maintenance on Wednesday 3/4/2013 at 9 AM. The system will not be available to users on 3/4/2013 from 9 AM to 5 PM. Kindly schedule your jobs accordingly.
Inconvenience Caused is regretted.
The formal inauguration of the VIRGO cluster on 28th March 2013, Thursday in CSB - 25 at 3 pm. Please note that on the same day we have the HPC in house symposium starting from 2.00 PM. The venue for both the functions are the same. We request all of you to participate and make the function a grand success.
Star4.18 installed
To load the latest Star4.18 version in virgo use the below path.
STAR4.18 = /sware/star4.18/bin
23rd January 2013
To load the latest MatlabR2012b version in virgo use the below path.
MatlabR2012b = /sfs1/sware/matlabr2012b/bin
Desktop User's may collect CD from computer centre or download it from ccftp.iitm.ac.in.
virgo is now available to the users. If you face any issue, please mail or call to HPCE Team
As you may have observed the file systems on Virgo have been rather unstable. We have been in touch with IBM to sort out this issue. IBM claims that they have identified the problem with GPFS and will start working on it from Tuesday the 15th of January onwards. They expect to complete the task by the end of the week.
Virgo will not be available to the users during this period from 15th to 20th of Janaury 2013.
Inconvenience caused is regretted.
Virgo cluster is working fine. Still there is some file system issue.IBM Engineers are working on this.
The IB Network of the Virgo cluster has Some problem & IBM is working on this.
As soon as the system is ready we will inform you.
The problem is temporarily solved. But the cause of the problem is not known and the system is under observation.
Duration of availability cannot be guaranteed till the cause is known and solved.
There is some filesystem issuse, IBM Engineers are working on it and it should be shorted out shortly.
We will upated you the status, once the issue is resolved.
Inconvenience caused is regretted.
21st December 2012
System is UP and Running.
VIRGO will be under hardware maintenance from 19/12/12 to 21/12/12 and the system will not be available to the users on these days.
Kindly schedule your jobs accordingly. Inconvenience caused is regretted.
Prior to certifying the final installation report of VIRGO cluster, we will have a users meeting. This is scheduled on 20/12/2012 at HSB 203 ( Physics Department Conference Room) at 3 P.M. IBM Engineers will be present at this meeting. Please attend this meeting and explain the problems that you are have in running the jobs on VIRGO.
The cmake, gsl-1.15 and itpp-4.2 is installed in Virgo Super cluster. The path to access the same as follows
CMAKE=/sware/cmake2.8
ITPP =/sware/itpp4.2
GSL =/sware/gsl1.15
Vega super cluster is out of warranty and will not be available from 5/11/2012 onwards
COMSOL 4.3 is now available in our Virgo Cluster at /sware/comsol/COMSOL43/bin.
Comsol 4.3 intallation instruction is now available here.
Happy to announce that the new IBM cluster VIRGO will be available to the users from Tuesday, 16-10-2012.
Please ssh to virgo.iitm.ac.in to access this machine. Since this is a new system there may still be some issues that need to be addressed and the machine may need reboot at short notice. The users are therefore requested to submit only short jobs for the first two weeks.
IBM is still working on the scheduler and will take some more days to complete it.Hence we have powered on the IB Cluster of Vega and will run it for 10 days.All queues except high memory queues will be allowed in IB Cluster.
This is just a temporary arrangement .
Once Virgo is ready, it will be released to users.
Wolfram is planning to conduct a Mathematica Seminar at IIT Madras
The Seminar will be on 5th October 2012 (10am to 12pm) at CAD Lab of Engineering Design Department. This seminar will be an unique opportunity to experience the breakthroughs that broaden the scope of Mathematica software and Wolfram System Modeler.
Those interested in participating may please register here http://10.93.203.91/form.
Computer Centre is organizing a workshop on GPU and CUDA programing on 27-28 September 2012.
Date : 27/9/2012 Time : 3 PM Venue : Engineering Design class room ED108
Date : 28/9/2012 Time : 10 AM Venue : CAD lab of ED department
Those who are interested may kindly register by sending a mail to hpce@iitm.ac.in
The Vega cluster is out of warranty and will be shut down on the 26th of this month. It will be dismantled and removed from the data centre.
We will be keeping a copy of all files in your home directory as of 20/9/2012 and you can ask for it when needed.
If you have some important files in the scratch or data, please copy them before the 25th of this month.
The Vega cluster is now partially up. The file system had crashed due to UPS failure and there are still some problems with the sfs1 ( home) file system.
After login please check your files and if there are any problems in accessing any of the files, please Contact our HelpDesk(5999) or mail us to hpce@iitm.ac.in.
One set of UPSs connected to Vega crashed because of battery problem and hence the Vega cluster is down.
UPS engineers are working on the problem and it is not clear when these UPSs will come up.
As soon as the UPSs are ready Vega will be made available to the users.
To load the latest Matlab 2012a version use the below path.
Matlab 2012a = /sfs1/sware/matlabr2012a/bin
To load the latest Ansys version use the below path.
For CFX = /sfs1/sware/ansys14/v140/CFX/bin
For Fluent14 = /sfs1/sware/ansys14/v140/fluent/bin
For icemcfd = /sfs1/sware/ansys14/v140/icemcfd/linux64_amd/bin
To load the latest Abaqus version use the below path.
Abaqus 6.11 = /sfs1/sware/abaqus6.11/Commands